Water cannot be allowed over the spillway while the spillway chute is being constructed. This will be completed in mid May if there are no setbacks.
Our only control of water level is opening/closing the silo drain and recent storms have filled the lake surprisingly fast.
We need to draw down the lake before each storm to maintain construction water levels. We will post as soon as possible as the completion date becomes more clear.
Plocher Construction has been working most days, even during wet weather, and expects to be able to finish the project on time.