The first week of work included staging on West Lake Common Area 1 (W1), and East Lake Common Area 8 (E8). Crane mats were laid and rip rap for E8 was delivered. With the nice weather, workers should be able to wrap up work at W1 on April 8 and then move the equipment to the north end of East Lake.
Workers will be come back to W1 to grate and lay good soil at the end of the project.