Apr 10, 2023 | Capital Projects, HOA / Board, Master Plan, News, Sediment
The final work on the Cove A depth restoration project will include more shoreline than originally planned. As shown in the photo below, there will be dirt coming out along the shoreline on West Lake Commons Area 1 and East Lake Commons Area 8 (E8). The contractor...
Apr 7, 2023 | Capital Projects, HOA / Board, Master Plan, News, Sediment
The first week of work included staging on West Lake Common Area 1 (W1), and East Lake Common Area 8 (E8). Crane mats were laid and rip rap for E8 was delivered. With the nice weather, workers should be able to wrap up work at W1 on April 8 and then move the equipment...
Apr 4, 2023 | Capital Projects, HOA / Board, Master Plan, News, Sediment
Stutz Excavation has begun removing dirt from West Lake Commons Area 1. Today the workers started clearing a path between some of the docks out into the lake. The Dunlap Lake 2023 silt basin improvements started April 4.
Mar 24, 2023 | Capital Projects, HOA / Board, Master Plan, Sediment, Uncategorized
The DLPOA Board is pleased to announce that as of 3/21/23 all permits are in hand, the IEPA and the Association executed the grant reimbursement document, the Board President Andrew Reznack signed the contract with Stutz Excavating to proceed as soon as possible....